Wind Power in France
General
The renewable energy objectives in France are defined by the 13 July 2005. Three targets are clearly defined in order to meet the overall objective. Firstly, the share of national renewable electricity production should reach 21% of the electricity consumption by 2010. In 2009 this share is about 13,5 % (source: Eurobserv'ER). Secondly, a 50% increase in the heat production coming from renewable sources. And thirdly, a 7% increase in the share of biofuels used for transport. The french government, in the framework of the annual investment in electricity production (PPI) in 2009, details the means used to achieve the development goals of renewable energy production.
The law named ‘Grenelle 1’ adopted on October 2008 confirms the willingness of the country to diversify its energy sources and meet the long-term target of 20% of renewable energy by 2020.The technical part of the Grenelle law, named law ‘Grenelle 2’ has been adopted on May 2010.
Renewable Electricity: wind power
The wind purchase prices
for electricity produced by wind turbines is defined by the decret of
17 November 2008 :
1. For onshore installations, the purchase
contract lasts 15 years and establishes the following rates: 8.2 c €
/ kWh for 10 years and between 2.8 and 8.2 c € / kWh for 5
years, depending on site productivity.
2. For Offshore
installations, the contract lasts 20 years and establishes the
following rates: 13 € c / kWh for 10 years, then between 3 and
13 € c / kWh for 10 years according to site productivity.
3.
French overseas departments and Mayotte
A single fare 11c € /
kWh has been set.
The objectives
established for wind sector of 11 500 MW for the 31 December 2012 (10
500 MW onshore and 1 000 MW for offshore wind farms) already seem to
be compromised. The country's target for 2020 of 25 000 MW (19 000 MW
onshore and 6 000 MW for offshore wind farms) appears as more viable.
The government has announced in may 2010 with the law 'Grenelle II'
some major changes in the wind turbine licensing system. The wind
turbine entered, from then on, in the scope of classified
installations for the protection of the environment (ICPE). The law
'Grenelle II' also consolidates the establishment of wind power
development zones (ZDE). For new wind parks, only those constructed
in a ZDE shall be able to benefit from the feed-in tariff. These
zones are defined by the regions, as a function of different
parameters such as the site's potential, the possibilities of
connection to the power grid and protection of the environment...New
wind parks have to contain at least 5 wind turbines and be distant
from 500 meters of housing area.
Future development of wind
sector in France will depend on the adapting capacity of the wind
market actor to this set of new constraints. From the government
point of view the implementation of this new mechanism should
streamline wind power project applications and curb the possibilities
of redress.
The feed-in-tariffs are indexed on inflation and working costs
in industry.
Detail of applicable
administrative procedures
Land-based
wind-turbines
As required by the Town
Planning Code, wind-turbines having a mast height greater than 12
metres are subject to planning permission. The Construction and
Housing Code submits wind- turbines having a mast height greater than
or equal to 12 metres to technical inspection.
As required by the
Environment Code, wind-turbines having a mast height greater than or
equal to 50 metres are subject to an impact study and public inquiry.
The operators must provide financial guarantees for the reinstatement
of the site on decommissioning of the facility. The Grenelle II law
provides for the methods for the creation of financial guarantees and
for the general provisions for decommissioning to be set by decree
before the end of 2010.
To benefit from the obligation to purchase
electricity produced, any new wind farm created since 15 July 2007
must be situated in a Wind Power Development Area (ZDE) which
requires a positive opinion from the municipalities hosting the
project.
In order to avoid scatter development, the Grenelle II
law provides for new wind power facilities to be comprised of at
least five wind-turbines to benefit from the obligation to purchase
in a ZDE. However, this rule does not apply to small facilities
comprising one wind- turbine of less than 250 kW and of less than 30
metres.
The Grenelle II law also provides for wind-turbines to
respect a minimum distance of 500 metres from housing. It also
provides for wind farms to be classified under the IPCE regime
(authorisation).
Sea-based wind-turbines
The Grenelle II law
provides for the abolition of all formalities required by the Town
Planning Code. It also provides for sea-based wind-turbines that the
purchasing obligation is not subject to being sited in a ZDE.
As
required by the Code of State-owned property, any project for the
siting of a wind farm in the public maritime domain must be subject,
for the wind-turbines themselves and for their connection to the
land, to an authorisation to occupy state land, together with a fee
set by the tax authorities. The decree relating to concessions for
the use of the public maritime domain excluding ports constitutes the
regulatory context of the state land occupation procedure.
As
required by the Environment Code, wind farms are subject to
authorisation as they constitute works in contact with the marine
environment and have a direct impact on this environment. They are
also subject to an impact study and public inquiry.
106/120
Moreover,
the Grenelle II law provides for the methods for the creation of
financial guarantees and for the general provisions for
decommissioning to be set by decree before the end of 2010. It also
provides for the classification under the IPCE regime for sea-based
wind farms.
The strategy for ensuring their development is based
on the launch of the call for tenders within zones defined as
relevant by the public authorities. This targeted procedure of calls
for tenders allows control of the execution calendar, optimisation of
the conditions for connection and acceleration of the obtention of
all authorisations required.
Future programme changes expected
No information is available on future programme changes.
Sources
Ministère de l'Ecologie, du Developpement Durable, des
Transports et du Logement
OBSERV'ER
http://ec.europa.eu/energy/renewables/transparency_platform_en.htm
The
National Renewable Energy Action Plans (NREAPs) are all published on
the Transparency Platform on Renewable Energy:
http://ec.europa.eu/energy/renewables/transparency_platform/action_plan_en.htm
(sourced July - December 2010)
Interactive EurObserv’ER Database
http://www.eurobserv-er.org
Last update: [January] 2011