
Wind energy in Poland
General
According to the Directive 2009/28/EC of the
European Parliament and of the Council on the promotion of the use of energy
from renewable sources the target for the share of energy from renewable
sources in gross final consumption of energy in the year 2020 for Poland is 15%
(in the year 2005 the share was 7.2%).
Renewable
electricity: wind
During the 2000-2011 period the installed capacity in wind turbines in Poland increased
from less than 20 MWe to 1.6 GWe
in 2011.
The following areas are particularly advantageous in
terms of wind resources:
Baltic Sea coast, in particular
in its eastern part,
North-eastern Poland
(vicinity of Suwałki and Gołdap),
Orographically diverse open areas of Warmia, Mazury and Pomorze,
Submontane areas of southern Poland
– primarily Podkarpacie and Lower
Silesia.
Apart from those areas,
after meeting certain requirements a number of potential wind farm sites are
also available in central Poland.
“Poland’s Energy Policy until 2030” provides
for implementing measures to increase energy security through the increase in
the use of renewable energy sources. However, such development would require
significant legislative changes allowing for development of grid infrastructure
and construction of new RES generating capacity.
The
support system of wind projects in Poland
is based on tradable
certificates of origin of the energy produced from RES (green certificates) and high
efficiency cogeneration, and system of grant subsidies
submitted for the investment and construction
phase. The total support (electricity price (197 zł/MWh ) + green
certificates (276 PLN/MWh)
can amount to 476 zł/MWh (122 EUR/MWh). However, the calculation is more complicated because
the prices are not fixed and they fluctuate on the market. Currently a new RES Act is under negotiation,
where the support system is constructed in a totally different way.
The biggest wind farm in Poland,
completed in 2010, is EDP’s 120 MWe
wind farm in Margonin, located in Wielkopolska.
Other significant installations constructed in 2010 were Kołobrzeg
(51 MWe) and Karnice (29,9 MWe), both owned by DONG
Energy. Also RWE extended their portfolio of wind farms in Poland by acquisition of the 32 MW Piecki and 50 MW Tychowo wind
farms.
In addition to the above-mentioned
projects which typically employ 2MWe turbines, smaller turbines, used for
smaller projects are quite popular in Poland – these are mostly “second-hand”
from repowering. Small and locally-owned enterprises
or private persons are usually operators in such cases, although the share of
electricity produced by such wind turbines in Poland is not significant. As presented on the map, bigger projects are
located usually in northern Poland,
which has the highest wind potential (pomorskie and zachodniopomorskie regions), whereas small developments are
characteristic for the interior of the country (especially kujawsko-pomorskie
regions), with 155 installations and total capacity of 166 MWe.
The concentration of wind farm
concepts in some areas is resulting in growing problems, blocking further development of many (even
well-prepared) projects. The problems usually concern the lack of grid
connection possibilities. In many areas, particularly in northern Poland,
all the connection capacity is currently blocked by large amount of wind farms,
having been already issued grid connection terms. Also numerous other barriers for wind power
development are reported by developers. The large concentration of wind farm concepts
in some areas raises the issue of the possible negative impact on the environment,
as well as frequently leads to greater social conflicts. Wind energy projects
have usually been met with enthusiasm by municipal authorities, because of the
higher expected tax income to the local budget. The legal regulations created
an opportunity to impose on the owner of the wind farm a property tax of 2% of
the value of the building part of the investment, which would be very
significant income to the municipality budget. However, in many cases the impact
of wind farms on the landscape and perceived potential negative impact on
tourism has become a political and economic issue.
Future programme
changes expected
In 2011 many investments that were
postponed last year for various reasons (result of financial crisis, delayed EU
funds etc.). The biggest development announced in Poland is 250 MW planned near Darłowo to be constructed by 2012.
The market potential of wind
power in Poland
by 2020 amounts to approximately 33,500 GWh. The
NREAP foresees a total installed capacity of 3.4 GWe
in 2015 and 5.6 GWe in 2020 for onshore installations
including 500 MWe micro installtions.
The offshore projects’ capacity is planned at the level of 500 MWe in the year 2020.
The amount of completed projects in Poland appears
to be very low, when compared with the bold ambitions of developers. Based on applications for grid connection
terms at the beginning of 2010 the grid operators estimate investors plan more
than 70 GWe. However this type of estimation is
definitely confusing – it’s enough to mention that in 2004 a similar metric
suggested that 9,500 MWe of projects were planned,
but only a small part was finalized. Thus the information originated from grid operators
has to be treated as a view of the potential scale of developers’ ambitions,
although not a practical guide to the real wind development possibilities in the
coming years.
To reduce the number of applications
for connection terms submitted by new developers, the amendment to the Energy
Law was introduced in March 2010, with requirements of advance payment
(nonrefundable) for connection fees being paid at application stage. Thus, by
September 2010, at some distribution system operators up to 90% of connection
applications were rejected. However, still the impact of regulatory changes on
the market was lower than expected. According
to PSE Operator, in January 2011 15 GWe of wind
projects had obtained connection terms and just 7 GWe
of those had signed connection contracts.
Circa 17 GWe of wind
farms are developed, mostly in northern and western Poland. In some regions, like zachodniopomorskie and wielkopolskie
regions there are around 4000 GWe under
development. Also several projects are in development in regions where the market
has developed slowly up to now, like southern Poland (dolnoslaskie
and podkarpackie). However, the prospects for
completing projects located there are unclear, because of several barriers,
mostly related to environmental limitations and weak
The future of the wind power sector
in Poland after 2010 will depend mainly on
final decisions about the way the EU Climate Package will be implemented in Poland,
including new directive 2009/28/EC about the promotion of the use of renewable
energy sources. In December 2010 the Ministry of Economy submitted to the
European Commission the National Renewable Energy Action Plan to 2020 (NREAP), required
by the directive and including the range of commitments for electric power generation from renewable
sources. The Polish target for 2020 is 15% of RES share in final energy
consumption. 26% of that (32,4 TWh)
is expected to be generated from renewable electricity. The official scenario assumes
that in 2020 there will be 5600 MW of wind turbines installed onshore, 500 MWe offshore and 550 MWe of small
wind turbines. This capacity is expected to deliver 47% of renewable
electricity.
Sources
National Renewable Energy Action Plan for Poland,
Warsaw 2010 URL: http://ec.europa.eu/energy/renewables/transparency_platform/doc/national_renewable_energy_action_plan_poland_en.pdf
PSEW Polskie Stowarzyszenie Energetyki Wiatrowej
EWEA European Wind Energy Association
Institute for Renewable Energy, Poland,
www.ieo.pl
Interactive
EurObserv’ER Database
http://www.eurobserv-er.org
Last update: March 2012
This information can be referenced
without permission provided that the source is mentioned completely and
correctly: 'Interactive EurObserv'ER Database,
http://www.eurobserv-er.org (date of last update)': January 2011
Suggestions for improvements to the policy description can be sent to EurObserv'ER by e-mail: project@eurobserv-er.org
The EurObserv'ER barometer is a project supported by
the European Commission within the DG TREN 'Intelligent Energy Europe' programme and by Ademe, the
French Environment and Energy management Agency. The EurObserv'ER
Barometer is the result of the investigation and research work of its authors.
The European Commission is not responsible for any use that may be made of the
information contained therein.